| EASTEREN POWER DISTRIBUTION COMPANY OF A.P.LIMITED |
| CORPORATE OFFICE:VISAKHAPATNAM |
| HVDS |
| List of officers who claimed Excess Bills |
| Sl. No |
Name of the Work |
Details of Excess Billing |
Excess Amount Claimed (In RS.) |
Name of the AE |
Name of the ADE/DE checkmeasured the Bill |
| 1 |
Inspection of HVDS works in Nidadavole Division in Eluru Circle during
Jan, Feb & Mar 2009 by TPQC |
1 No LT side cross arm with strut
2 Strut pole not provided but billed
3 New pole billed but not erected
4 Stay set with concreting not provided but claimed
5 CI pipe not provided but billed |
12,789/- + 83900/- (to wards cost of defective meters |
Sri.P.M.Johnson, AAE/Construction/Nidadavole |
Sri.Y.David, ADE/Construction/ Nidadavole |
| 2 |
Inspection of HVDS works in Eluru Division in Eluru Circle during Mar
2009 by TPQC |
1 No LT side cross arm with strut
2 New pole billed but not erected
3 Existing poles billed as new poles
4 Strut pole not provided but billed
5 Stay set with concreting not provided but claimed
6 No dead end clamps provided for AB cable |
30898/- + 143800/- (to wards cost of defective meters |
Sri.P.Nageswara Rao, AE/Construction/Eluru |
Sri. T.Sasidhar, ADE/Construction/Eluru |
| 3 |
Inspection of HVDS works in T.P.Gudem Division in Eluru Circle by M/s.Godavari
Electrical Consultants, Rajahmundry, the third party Q.C. agency |
1) LT side cross arms with strut were not provided for the DTRs
2) Concrete for the11 KV stay was not done but claimed in the bill
3) 11 KV stay set with concrete were not provided but claimed in the bill.
4) Concrete was not provided for the PSCC pole but claimed in the bill. |
15,782/- |
Sri..G.Krishna Reddy, AAE/Construction/ T.P.Gudem |
Sri.E.Mohan, ADE/Construction/ T.P.Gudem |
| 4 |
Inspection of HVDS works in T.P.Gudem Division in Eluru Circle during
Feb & Mar 2009 |
1 LT side cross arm with strut not provided for the DTR structure
2 LT connectors not provided
3 'T' clamps not provided for jumpers
4 Dead end clamps not provided for LT AB cable
6 Strut pole not provided but billed.
7 Old pole with 'V' cross arm claimed as new pole in the bill. |
1,17,998/- + 180865/- (to wards cost of defective meters |
Sri.G.Krishna Reddy, AAE/Construction/ T.P.Gudem |
Sri.E.Mohan, ADE/Construction/ T.P.Gudem |